Site icon Exam4Training

Which of the following will be VITAL for ensuring that the company meets the deadlines?

A client has ordered a large project from a company. This project has several critical components and a fixed schedule.

Which of the following will be VITAL for ensuring that the company meets the deadlines?
A . proper job costing
B . confirming lead times
C . qualifying the customer
D . confirming price changes

Answer: B

Explanation:

For a project with several critical components and a fixed schedule, confirming lead times is vital. Lead times refer to the amount of time it takes for components to be delivered from the supplier to the project site. By confirming and managing lead times, the company can ensure that all necessary components arrive on time, preventing delays and enabling the project to proceed according to the planned schedule. This is essential for meeting deadlines and ensuring project success.

Reference: Axis Communications – Project Planning and Management Supply Chain and Logistics Best Practices

Latest CTS Dumps Valid Version with 193 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version