Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?

A client has provided a list of deliverables to include in the project scope .

Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?
A . Requirements traceability matrix
B . Gantt chart
C . SWOT analysis
D . Project charter

Answer: A