You are about to release a test progress report to a senior manager, who is not a test specialist.
Which of the following topics should NOT be included in the test progress report? 1 credit
A . Product risks which have been mitigated and those which are outstanding.
B . Recommendations for taking controlling actions
C . Status compared against the started exit criteria
D . Detailed overview of the risk-based test approach being used to ensure the exit criteria to be achieved
Answer: D