You are about to release a test progress report to a senior manager, who is not a test specialist .
Which of the following topics should NOT be included in the test progress report? 1 credit
A . Product risks which have been mitigated and those which are outstanding.
B . Recommendations for taking controlling actions
C . Status compared against the started exit criteria
D . Detailed overview of the risk-based test approach being used to ensure the exit criteria to be achieved
Answer: D
Latest CTFL Foundation Dumps Valid Version with 338 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund