Which of the following tools would a project manager use to determine the root cause of an issue?
Which of the following tools would a project manager use to determine the root cause of an issue?
A . Pareto Chart
B . Ishikawa Diagram
C . Histogram
D . Monte Carlo Analysis
Answer: B