Which of the following tools will the project manager MOST likely use?
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project.
Which of the following tools will the project manager MOST likely use?
A . Dashboard
B . Gantt chart
C . Work breakdown structure
D . Requirements Traceability Matrix
Answer: A
Explanation:
A dashboard is a tool that the project manager will most likely use to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a graphical tool that displays key performance indicators (KPIs), metrics, and data related to a project using charts, graphs, tables, or other visual elements. A dashboard can help to provide a quick and easy overview of the project status and performance and highlight any issues or risks that need attention.
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund