Which of the following tools should the project team select to determine the possible origins of the increased costs?

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns.

Which of the following tools should the project team select to determine the possible origins of the increased costs?
A . Pareto chart
B . Fishbone diagram
C . Process diagram
D . Run chart

Answer: B