Which of the following tools best provides transparency into the progress throughout the sprint?

A development team has finished identifying the tasks they will be accountable for during the next sprint.

Which of the following tools best provides transparency into the progress throughout the sprint?
A . Burndown chart
B . Gantt chart
C . Hours expended chart
D . Management baseline chart

Answer: A