Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?
A . Fast tracking
B . Compressing
C . Float
D . Crashing

Answer: A