Which of the following techniques is MOST likely to be used to complete the project on time?
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time.
Which of the following techniques is MOST likely to be used to complete the project on time?
A . Throttling
B . Crashing
C . Resource leveling
D . Resource smoothing
Answer: B
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170