There are four parallel paths on a network diagram. The summary duration of each path is below:
A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks
Which of the following tasks are on the critical path?
A . A, C, G
B . A, B, F
C . D, E, H
D . D, B, F
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund