Which of the following steps should you take to ensure this consultant’s utilization calculation will be calculated correctly?
Your company hired its first part-time employee that needs to be set up as a Consultant in PSA. They will work about 20 hours a week instead of the normal 40 hours a week.
Which of the following steps should you take to ensure this consultant’s utilization calculation will be calculated correctly?
A. Create a new "Role" indicating the user is a Part Time Consultant
B. Create a new Part Time "Work Calendar" for 20 hours
C. Create a new "Utilization Calculation" labeled Part Time
Answer: B
Latest PSA Sysadmin Dumps Valid Version with 60 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments