Which of the following steps should the project manager perform NEXT?
A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000.
Which of the following steps should the project manager perform NEXT?
A . Wait until the change requests are approved by the CC
C . Approve the changes because the additional functionality is required to complete the process.
D . Speak with the project sponsor and provide a detailed analysis of the changes and impacts to the project budget.
E . Schedule the changes as part of the second phase of the project when additional
funding will be available and work can be completed.
Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 292
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund