Which of the following steps should take place NEXT?
A customer has requested additional features for an active project.
Which of the following steps should take place NEXT?
A . Implement the requested changes.
B . Evaluate the impact of the changes.
C . Update all project documents.
D . Submit the requested changes to the CC
Answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.293
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments