Which of the following steps should take place NEXT?
A customer has requested additional features for an active project.
Which of the following steps should take place NEXT?
A . Implement the requested changes.
B . Evaluate the impact of the changes.
C . Update all project documents.
D . Submit the requested changes to the CC
Answer: B
Explanation: