Which of the following steps should be taken first?
A technician needs to apply a high-priority patch to a production system.
Which of the following steps should be taken first?
A . Air gap the system.
B . Move the system to a different network segment.
C . Create a change control request.
D . Apply the patch to the system.
Answer: C
Explanation:
= A change control request is a document that describes the proposed change to a system, the reason for the change, the expected impact, the approval process, the testing plan, the implementation plan, the rollback plan, and the communication plan. A change control request is a best practice for applying any patch to a production system, especially a high-priority one, as it ensures that the change is authorized, documented, tested, and communicated. A change control request also minimizes the risk of unintended consequences, such as system downtime, data loss, or security breaches.
Reference = CompTIA Security+ Study Guide with over 500 Practice Test Questions: Exam SY0-701, 9th Edition, Chapter 6, page 235. CompTIA Security+ SY0-701 Exam Objectives, Domain 4.1, page 13.
Latest SY0-701 Dumps Valid Version with 77 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund