You want to configure notifications for SAP Fiori in an embedded deployment scenario.

Which of the following steps do you have to perform? There are 3 correct answers to this question.
A . Maintain and activate push channel with ID SAP_WEBSOCKET.
B . Create bgRFC destination IWNGW_BGRFC.
C . Activate ICF service /sap/opu/odata4 for OData V4.
D . Provide the backend system alias.
E . Register bgRFCinbound destination IWNGW_BEP_OUT_ BGRFC

Answer: B, C, E