Team members have reported that meetings are poorly attended and unproductive.
Which of the following steps can the project manager take to make the meetings more productive?
A . Discontinue the meetings with the poorest attendance.
B . Decrease the length of the meetings.
C . Distribute an agenda before each meeting.
D . Document team member attendance and report it to management.
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326