Exam4Training

Which of the following statements refers to how scope is managed in a linear project but not an iterative project?

Which of the following statements refers to how scope is managed in a linear project but not an iterative project?
A . Teams can act on new knowledge to change the scope.
B . Teams can re-prioritise requirements within the scope.
C . The scope of work is the starting point for the implementation of change control.
D . Scope definition is assumed to be fixed for the whole project

Answer: D

Latest APM-PFQ Dumps Valid Version with 354 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version