Which of the following statements best describes risk management in the ADM?
A . Risk analysis is best conducted in the Architecture Vision phase so that the risk is eliminated in subsequent phases
B . Risk analysis should be carried out first in the Migration Planning phase
C . Risk analysis is outside the scope of enterprise architecture projects
D . Risk is pervasive in all enterprise architecture activity and should be managed in all phases of the ADM
E . The only risks that are within the scope of enterprise architecture are technological risks
Answer: D