Which of the following statements about TOGAF Building Blocks and their use in the ADM cycle is correct?

Which of the following statements about TOGAF Building Blocks and their use in the ADM cycle is correct?
A . Building Blocks become more implementation-specific in Phase E
B . Building Blocks in phases D, E and F are evolved to a common pattern of steps
C . Building Blocks should be identified in abstract form as part of the Preliminary Phase
D . Building Blocks should be first selected in Phase D

Answer: A