Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?
K2 1 credit
A . Test reporting activities can’t be influenced by the use of an iterative lifecycle model with short iterations
B . Test reporting activities are not important for projects adopting an iterative lifecycle model with short iterations
C . Test reporting activities are less important for projects adopting an iterative life cycle model with short iterations. They should be performed at the end of the last iteration
D . Test reporting activities are still important with an iterative lifecycle. The reports can be
used to conduct post-iteration review sessions before starting with the next iteration
Answer: D