Which of the following software development lifecycle models requires the earliest involvement from the Test Analyst?

Which of the following software development lifecycle models requires the earliest involvement from the Test Analyst?
A . V-model
B . Embedded iterative model
C . Agile development model
D . Maintenance lifecycle

Answer: C

Explanation:

The agile development model requires the earliest involvement from the test analyst because it is a flexible and iterative approach that delivers software in short cycles called sprints. The test analyst plays a key role in planning, designing, executing, and reporting on the testing activities for each sprint.

Reference =

ISTQB Certified Tester Advanced Level Overview of Syllabi1, page 10

ISTQB Certified Tester Advanced Level Syllabus Technical Test Analyst2, page 2 Understanding the SDLC: Software Development Lifecycle Explained3, section “Agile model”