Which of the following should the project manager use to identify the MOST important causes?
During a quality analysis review, the causes of several issues have been highlighted.
Which of the following should the project manager use to identify the MOST important causes?
A . Ishikawa diagram
B . Scatter diagram
C . Pareto chart
D . Decision tree
Answer: C
Explanation:
The Pareto chart should be used to identify the most important causes of issues during a quality analysis review. The Pareto chart is a graphical representation of the frequency and impact of different causes, helping to identify the most common and impactful causes.
Reference: CompTIA Project+ Study Guide Section 3.3.3
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments