Which of the following should the project manager do NEXT?
A project manager is informed that a team member would like to enhance the code with an additional function.
Which of the following should the project manager do NEXT?
A . Submit a change request.
B . Evaluate the impact of the change.
C . Get approval from the CC
E . Communicate the change to stakeholders.
Answer: B