Which of the following should the project manager do NEXT?
A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes.
Which of the following should the project manager do NEXT?
A . Gain approval for the changes.
B . Identify the approval authority.
C . Implement the changes.
D . Create an emergency change request.
Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294