Which of the following should the project manager do NEXT?
A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk .
Which of the following should the project manager do NEXT?
A . RF1
B . RFP
C . RFQ
D . Change request
E . Request for bid
Answer: E