Which of the following should the project manager do NEXT?
A project has a of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the
CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget .
Which of the following should the project manager do NEXT?
A . Add the required work to complete the project behind $892,500.
B . Evaluate the impact and justify adding new work to the project.
C . Obtain approval from the CC
E . Request a budget increase of $170,000.
Answer: C