Which of the following should the project manager do FIRST to minimize negative impacts to the project?

A key team member found a new job and will be leaving in two weeks .

Which of the following should the project manager do FIRST to minimize negative impacts to the project?
A . Request a replacement from the project sponsor.
B . Contact human resources to initiate the termination process.
C . Involve the legal department for contract review.
D . Inform executive management about attrition.

Answer: A