Which of the following should the project manager do FIRST?

A team member was replaced on a project by a new team member of equal capability.

Which of the following should the project manager do FIRST?
A . Resource loading
B . Resource leveling
C . Prioritizing tasks
D . Allocating resources

Answer: D