A PM learns about some communication issues with different stakeholders and team members.
Which of the following should the PM do NEXT?
A . Escalate the communication issues.
B . Implement a communication platform.
C . Review the communication plan.
D . Talk with the head of the PMO.
Answer: C
Explanation:
The project manager should review the communication plan after learning about some communication issues with different stakeholders and team members. A communication plan is a document that defines and documents the communication goals, strategies, methods, channels, frequency, roles, and responsibilities for a project. A communication plan can help to facilitate effective and timely communication among all stakeholders involved in a project and avoid confusion, misunderstanding, or conflicts.