A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees.
Which of the following should the PM do next to comply with the new legislation?
A . Use only full-time employees even if the project is delayed.
B . Hire all team members to avoid any delay in the project.
C . Close the contract and pay the contractors cash for the remainder of the project.
D . Look for an overseas vendor to finalize the project work.
Answer: A
Explanation:
In response to new legislation requiring the release of contractors or their conversion to full-time employees, the project manager should prioritize compliance with the law. This may involve using only full-time employees, even if it results in project delays. The focus should be on legal compliance and the ethical treatment of workers, rather than solely on project timelines.
Reference = The answer is based on standard project management practices and the typical response to changes in legislation affecting project staffing. For detailed information, please refer to the CompTIA Project+ Study Guide and other official CompTIA resources.