Which of the following should the PM do NEXT?

A PM learns about some communication issues with different stakeholders and team members.

Which of the following should the PM do NEXT?
A . Escalate the communication issues.
B . Implement a communication platform.
C . Review the communication plan.
D . Talk with the head of the PMO.

Answer: C

Explanation:

The project manager should review the communication plan after learning about some communication issues with different stakeholders and team members. A communication plan is a document that defines and documents the communication goals, strategies, methods, channels, frequency, roles, and responsibilities for a project. A communication plan can help to facilitate effective and timely communication among all stakeholders involved in a project and avoid confusion, misunderstanding, or conflicts.

Latest PK0-005 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments