Which of the following should be used to complete the tasks on time?
A project manager does not have enough time to complete several tasks on a critical path.
The budget is a low concern.
Which of the following should be used to complete the tasks on time?
A . Fast-track the tasks.
B . Utilize positive float.
C . Crash the schedule.
D . Remove the critical path
Answer: A