Which of the following should be used to complete the tasks on time?

A project manager does not have enough time to complete several tasks on a critical path.

The budget is a low concern.

Which of the following should be used to complete the tasks on time?
A . Fast-track the tasks.
B . Utilize positive float.
C . Crash the schedule.
D . Remove the critical path

Answer: A