An organization created a formalized plan for a large project.
Which of the following should be the first step in the project management plan?
A . Estimate time required to complete the whole project.
B . Determine the responses to expected project risks.
C . Break the project into manageable components.
D . Identify resources needed to complete the project
Answer: A