Which of the following should be done to prevent this issue from reoccurring?

A storage area network (SAN) was inadvertently powered off while power maintenance was being performed in a datacenter. None of the systems should have lost all power during the maintenance. Upon review, it is discovered that a SAN administrator moved a power plug when testing the SAN’s fault notification features.

Which of the following should be done to prevent this issue from reoccurring?
A . Ensure both power supplies on the SAN are serviced by separate circuits, so that if one circuit goes down, the other remains powered.
B. Install additional batteries in the SAN power supplies with enough capacity to keep the system powered on during maintenance operations.
C. Ensure power configuration is covered in the datacenter change management policy and have the SAN administrator review this policy.
D. Install a third power supply in the SAN so loss of any power intuit does not result in the SAN completely powering off.

Answer: A

Latest CS0-002 Dumps Valid Version with 220 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments