Which of the following should a Scrum Master do to start a project?
Which of the following should a Scrum Master do to start a project?
A . Ask the Lead Developer to explain the IT architecture.
B. Ask the Development Team to introduce themselves to each other and tell about their skills and background.
C. Ensure, that all team members have a first ticket assigned to them.
Answer: B
Explanation:
The team is self-organizing – the Scrum Master does not assign tickets to them. There are no Lead Developers in Scrum.