Which of the following settlement type can you use?

Your project requires the settlement of a condition contract in SAP S/4HANA.

Which of the following settlement type can you use? Note: There are 3 correct answers to this question.

A. Invoice settlement

B. Delta settlement

C. Periodic settlement

D. Partial settlement

E. Final settlement

Answer: B,D,E