Which of the following rules do you consider?
You created a key figure and want to add calculations.
Which of the following rules do you consider? Note: There are 2 correct answers to this question.
A . Aggregation calculations using SUM or MAX functions must be based on a higher aggregation level.
B. The calculation chain for a key figure must always result in a calculated key figure.
C. Key figures can be calculated across different planning levels.
D. All key figure calculations have calculation inputs, which can be marked as stored or calculated.
Answer: C,D