Which of the following risk strategies should the project manager adopt?

A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success.

Which of the following risk strategies should the project manager adopt?
A . Exploitation
B . Avoidance
C . Acceptance
D . Mitigation

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 239

Latest PK0-004 Dumps Valid Version with 574 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments