Which of the following risk strategies prevents a risk from impacting a project?

Which of the following risk strategies prevents a risk from impacting a project?
A . Accept risk
B . Mitigate risk
C . Avoid risk
D . Transfer risk

Answer: C

Explanation:

Reference https://pm4id.org/chapter/11-2-risk-management-process/