An software engineer is applying new updates to a program in a sandbox environment.
Which of the following risk strategies best describes this practice?
A . Transfer
B . Mitigate
C . Avoid
D . Accept
Answer: B
Explanation:
Mitigate is a risk strategy that involves taking actions to reduce the probability or impact of a risk. By applying new updates to a program in a sandbox environment, the software engineer is testing the changes before implementing them in the actual system, thus minimizing the chance of errors or failures that could affect the project1.