On a hydroelectric power project, damage to life and property due to floods and landslides has been identified as a potential risk.
Which of the following Risk Assessment Techniques can be used by the Scrum Team to assess the potential risk, and its impact on project objectives?
A . Probability Impact Grid.
B. Probability Trees.
C. Pareto Analysis.
D. Expected Monetary Value.
Answer: A
Explanation:
Reference: https://scrumstudy.wordpress.com/2014/08/27/scrum-master-how-are-risks-assessed-in-a-scrumproject/