The Bonus Program is perceived by management to be critical. Defects in the program would almost immediately lead to financial loss. In the past an improvement program has been run to implement review based on IEEE 1028. Knowledge and skills on both formal and informal reviews are available. There is also an existing pool of review leaders.
Which of the following review types would you choose to review the program? 2 credits [K4]
A . Informal review
B. Inspection
C. Walkthrough
D. Management review
Answer: B