Which of the following review types would be recommended at the start of each Sprint, for the reason given?
A . An inspection, to find errors in the user-stories.
B. A management review, to check that the user-stories will accurately reflect the rules for accessibility.
C. A walkthrough of the set of user-stories, to ensure that the developers and testers understand what is to be built.
D. A technical review of the test plan, to ensure that the developers are aware that they must produce good quality code.
Answer: C