Which of the following represents the program manager’s strategy?

A program manager assigns project managers lo five component projects and continues to develop the program team.

Which of the following represents the program manager’s strategy?
A . Rotate the responsibility for risk assessment among the program components
B. Coach the project managers to manage project resources
C. Cross-train the project managers to share expertise
D. Prepare the project managers to assume larger roles with more responsibility.

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments