Which of the following represents the number of days the project schedule will be delayed?

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks.

Which of the following represents the number of days the project schedule will be delayed?
A . Zero
B . One
C . Two
D . Three

Answer: D

Latest PK0-004 Dumps Valid Version with 574 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments