Which of the following represents the number of days the project schedule will be delayed?
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks.
Which of the following represents the number of days the project schedule will be delayed?
A . Zero
B . One
C . Two
D . Three
Answer: D