Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?

Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?
A . Decision makers may be deterred from taking responsible risks.
B . The entity will realise that its approach to project appraisal is flawed.
C . The audit itself will waste time.
D . The entity may withdraw from a project without good cause.

Answer: A