A project manager has decided to wait until all requirements are developed to initiate testing.
Which of the following relationship dependencies is the project manager using?
A . Start-to-finish
B . Finish-to-finish
C . Finish-to-start
D . Start-to-start
Answer: C
Explanation:
A finish-to-start dependency is a type of relationship dependency in project management, where the start of one task depends on the finish of another task12. In this case, the project manager is using a finish-to-start dependency, because testing cannot start until requirements development is finished. This implies that testing is a successor task, and requirements development is a predecessor task. A finish-to-start dependency is the most common type of dependency in project management, and it ensures that tasks are performed in a logical sequence34.
Reference = CompTIA Project+ Certification Study Guide5, CompTIA Project+ Certification Exam Objectives6, Understanding Dependencies in Project Management [2023] * Asana1, Dependencies in Project Management | Smartsheet2, Understanding Task Dependencies in Project Management3, What are Dependencies in Project Management? – KnowledgeHut4
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund