You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).
Which of the following properties for the resulting dependent requirements applies?
A . In multi-level backward scheduling, dependent requirements are calculated to the exact second.
B . If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.
C . When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.
D . In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.
Answer: D
Latest C_TSCM42_67 Dumps Valid Version with 106 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund